Timeline for renovation works at 33a Chapel Street in Appleby, Cumbria
Scaffolding goes up
Scaffolding goes up at the front of the house, ready for works to start on the roof.
Scaffolding goes up at the front of the house, ready for works to start on the roof.
Cabling gets under way, starting with the top two floors.
Timber frames for new stud walls go in upstairs, creating the rooms that will be the bedroom and bathroom, and the corridor leading to the stairs between the first floor and top floor.
The new layout of the house comes into shape as some internal walls are taken down.
The old concrete floor is dug out, making way for the new insulated limecrete floor to go in.
33a Chapel Street welcomes the public for a look around for the first time, during Heritage Open Weekend and as part of Cumbria Green Build Festival 2018.
The very first video diary charting progress on the renovation goes live on the CAfS YouTube channel.
Crews from ITV Border and That’s Cumbria TV visit the house, with reports on that evening’s news
Work begins on stripping out the house, removing cement render on inside walls
The house changes hands and the project to renovate it can get under way